Building on Your Land in Deschutes County: Septic, Permits and a Shop

Own vacant land in unincorporated Deschutes County? Settle septic, your zone and overlays, a shop, permit order and builder checks before you design.

Don Healy, founder of Sand & Sage Solutions / 24 min read
Flat sagebrush lot in Central Oregon with a rough dirt track across it and juniper trees along the horizon.
A Central Oregon lot before any site work.

Before you pick a floor plan, sign with a builder or order a shop kit on land you own, settle four things. Those are your zone and overlay zones, your septic site evaluation, what the county allows for a shop, and the order of permits. Each can change where the house and shop go, or what they cost.

This guide covers unincorporated Deschutes County only. Bend, Redmond, Sisters and La Pine are cities, and city rules apply or differ inside their limits. In our experience, a mailing address in La Pine or Sisters does not mean the lot is inside that city, so confirm city limits first.

Your base zone sets the main rules for your lot. An overlay zone adds its own review on top of it, and the county code calls it a combining zone. The examples here are two county zones, Rural Residential (RR-10, DCC 18.60) and Multiple Use Agricultural (MUA-10, DCC 18.32). If DIAL, the county’s online property lookup, shows another zone, such as farm, forest or an unincorporated community, uses and setbacks differ (Deschutes County Code Title 18), so ask Planning.

This is general information, not legal, title or engineering advice. County pages and fees change. The county says to contact Planning to confirm before acting (planning@deschutes.org, 541-388-6560).

What should you check first on land you own in Deschutes County?

Check three records first: your zone and overlay zones, your permit history, and your recorded CC&Rs. CC&Rs are the private rules your subdivision recorded. The county points owners to its Summary Property Report and to DIAL for zoning, acreage and prior permits. Our DIAL guide shows how.

In RR-10 and MUA-10, a house is a use permitted outright, meaning the zone lists it as an allowed use (DCC 18.60.020(A) and DCC 18.32.020(B)). Other reviews still apply: overlay zones, lot of record checks where required, septic, access and building permits (county building permit steps).

Overlay zones add review where they apply. Ask Planning which ones cover your lot.

  • Landscape Management covers areas within one-fourth mile of roads the county has identified as landscape management corridors (DCC 18.84.020). A new structure that needs a building permit, house or shop, needs site plan approval first, which is the county’s design review of your plot plan, elevations, colors and landscaping (DCC 18.84.050 and DCC 18.84.070).
  • Flood Plain covers areas the county’s flood insurance study marks as Special Flood Hazard Areas (DCC 18.96.020). A house there is a conditional use, meaning a use the county may allow subject to the code sections that apply (DCC 18.96.040(C)). No new house or accessory structure may be built in the floodway (DCC 18.96.060(A)). The floodway is the channel and the land beside it that must stay open to carry flood water (DCC 18.04.030). The one exception the code lists is replacing a house that lawfully existed when that rule took effect (DCC 18.96.060(A)). Elsewhere in the flood plain, a new house or accessory structure is allowed only if you show no location outside the flood plain exists on your property (DCC 18.96.060(B)). The flood plain follows the Flood Insurance Study the code adopts, revised September 28, 2007 (DCC 18.96.020). The county’s DIAL help page names a flag, “Is Within the FEMA 100 Year Flood Plain” (county DIAL page), so check that flag and confirm with Planning.
  • Wildlife Area, Surface Mining Impact Area and Airport Safety zones add their own review where they apply (DCC 18.88, DCC 18.56 and DCC 18.80). Some carry two review tracks with different numbers, so ask Planning which applies.

Setbacks are the minimum distances from your lot lines. Front setbacks depend on the class of road your lot fronts: local, collector or arterial. The table shows front, side and rear distances for RR-10 (DCC 18.60.040) and MUA-10 (DCC 18.32.050).

Zone Front: local / collector / arterial road Side Rear
RR-10 20 / 30 / 50 feet 10 feet 20 feet
MUA-10 20 / 30 / 80 feet 20 feet 25 feet

Conditions that change those numbers:

  • MUA-10 allows a 10 foot side setback for lots created before November 1, 1979 that are one half acre or less (DCC 18.32.050(B)).
  • In MUA-10, a dwelling needs 100 feet from a side or rear lot line that abuts property receiving special assessment for farm use, a farm tax status (DCC 18.32.050(B) and (C)).
  • In RR-10, structures must sit at least 100 feet from the ordinary high water mark of a river, stream or lake (DCC 18.60.050). The distance is measured from that line to the nearest point of the structure (DCC 18.04.030). Ask Planning where the line is on your lot.
  • In RR-10, a greater setback required by building codes also applies (DCC 18.60.040(E)).

In RR-10, a lot with more than one front lot line and collector or arterial frontage may get 20 foot front setbacks, as a discretionary alternative, with the road authority’s written authorization (DCC 18.60.040(A)(1)). In MUA-10, the 80 foot arterial setback applies unless the county approves other provisions for combining accesses (DCC 18.32.050(A)). Confirm your numbers with Planning.

Both zones require a solar setback from the north lot line for every new structure, a shop included, worked out for your site from building height and slope (DCC 18.116.180). It keeps a new building from shading the lot to the north in winter, so structures sit as far south as is practical (DCC 18.116.180(A)).

Setbacks are measured from your lot lines. If you are not sure where yours are, our property pins guide explains how to find the markers.

A lot of record is a lot or parcel that met the zoning and land division rules when it was created. A tax lot made only by an assessor’s roll change is expressly not one (DCC 18.04.030). The code requires county verification only before listed permits, with exceptions, including lots from a recorded, county approved plat (DCC 22.04.040). The county tells applicants to contact Community Development to verify a legal lot.

County Code Enforcement says it is not able to assist with enforcing HOA requirements or any civil requirements that are not County Code (Code Enforcement page). In our experience, read your CC&Rs before you design. One Central Oregon subdivision’s recorded rules set larger setbacks than the county’s, a minimum house size and an 18 month construction limit. See our HOA design review guide.

What does septic involve in Deschutes County, and what does it cost?

Septic starts with a county site evaluation, before any septic or building permit, unless a valid one is already on file (Site Evaluation Research Checklist). The county’s onsite wastewater pages publish fees, not installed prices, which come from quotes by installers licensed by the Oregon Department of Environmental Quality (DEQ) for the system your evaluation names. The line “New site evaluation, single family dwelling” is $1,327 plus a $159 DEQ surcharge, on a FY 2027 fee schedule whose pages are still marked Proposed. Confirm the amounts with Community Development. For a rough planning number on permits, water, power and septic, try the free SiteFacts Land Budget Calculator.

Open drainfield trenches and a septic tank excavation on a flat Central Oregon lot, with an excavator and a skid steer in the background.
Drainfield trenches and the tank excavation on a Central Oregon home site. The drainfield location came first; the house was placed around it.

A site evaluation is the county’s soil and site review for a septic system. A county Environmental Health Specialist’s report gives the approved drainfield location, the area where treated wastewater soaks into the ground. It also gives the type and size of system, or the reasons for denial (county site evaluation page).

Before you apply, you prepare at least three test pits, holes dug so the evaluator can see the soil layers, and have your property corners located and staked or flagged (test pit requirements). The county recommends, but does not require, a DEQ licensed installer to dig them (installer recommendation). You apply online through Oregon ePermitting (Site Evaluation Application Guide).

The county attempts to complete site evaluations within 30 days, and state rules set no required timeframe (30 day target). It cannot do one on frozen or snow covered ground, so winter can postpone it (winter limits).

Item FY 2027 county fee
New site evaluation, single family dwelling $1,327 plus $159 DEQ surcharge
Construction installation permit: first 1,000 gallons projected daily sewage flow, standard on-site system $1,884 plus $159 DEQ surcharge
Authorization notice: Field visit required $1,023 plus $159 DEQ surcharge
Authorization notice: No field visit required $492 plus $159 DEQ surcharge

The last two lines are alternatives. One or the other applies, depending on whether the county needs a field visit, and the schedule does not say which applies to a shop, so ask the Onsite Wastewater Division (fee schedule PDF). The county’s Onsite Authorization guide says an Authorization Notice is required when an owner with an existing onsite septic system wants to place it into service, reconnect, or increase its projected daily flow. On a lot with no septic system yet, the septic for a house and shop goes through the site evaluation and installation permit described above (county site evaluation page).

The fee schedule does not say whether alternative system lines replace or add to the standard line. Ask the Onsite Wastewater Division before you total a non-standard system.

In southern Deschutes County, DEQ staff review specific properties and decide the level of treatment site by site, when a property needs a new system or a major repair. Where there is increased risk to nearby drinking water wells or surface waters, the typical result is a nitrogen-reducing system, which adds treatment to protect those waters (county southern Deschutes page). That page prints no boundary map, so ask which review applies to your lot.

When our founder built his own home in Central Oregon, the test pits marked where the drainfield could go. The tank then had to sit close enough to the house for gravity flow. He found that those two facts placed the house. That is one owner’s experience, not a county rule.

Can you build a house and a shop on your land?

In RR-10 and MUA-10 you can plan both, but the county’s order rule comes first. The primary use of the lot, normally the house, must be established or applied for before the county issues a building or land use permit for an accessory structure such as a shop (DCC 18.116.040(A)). The county’s accessory buildings brochure says applying for a home building permit establishes it.

A shop can come first in a limited form. The code lists three cases where a permit can issue with no primary use (DCC 18.116.040(A)(1)). Two are narrow: a building permit for a ramada or carport, and permits sought to correct existing code violations. The third is the one that fits a shop. It covers a structure, or structures, that meet all of these, if all other criteria for issuance are met (DCC 18.116.040(A)(1)(c)):

  • No more than 2,000 square feet combined.
  • No windows.
  • Only one floor.
  • An operable garage door.
  • No plumbing or stack vents, the plumbing vent pipes, through the roof or walls.
  • No need for plumbing or mechanical permits.

The brochure also lists a walk in door, which it calls a man door, as permitted on a shop that comes first (accessory buildings brochure). That section lists plumbing and mechanical permits but not electrical, so ask Planning before you plan wiring in a shop that comes first (DCC 18.116.040(A)). Wiring a shop needs its own residential electrical permit (electrical permit guide).

A small detached shop with sheathed walls and roof, a wide door opening and one window, on a Central Oregon lot at dusk.
A small shop going up on a Central Oregon home site, outside Deschutes County. Its window alone would rule it out as a shop built before the house under the Deschutes County rule above.

After a primary use is established or applied for, the RR-10 and MUA-10 sections we reviewed set no separate size cap for a shop. The zone standards apply to it like any structure:

  • A 30 foot height limit, with exceptions (DCC 18.60.060(B) and DCC 18.32.040(C)).
  • The setbacks in the table above, plus the solar setback.
  • In RR-10 only, a limit of 30 percent of the lot covered by structures (DCC 18.60.060(A)). We found no coverage limit in the MUA-10 section we read (DCC 18.32.040), so ask Planning.

A side or rear setback may drop to five feet for a small accessory structure. It must be more than 65 feet from the front lot line, detached from other buildings by five feet or more, one story, and no more than 450 square feet (DCC 18.116.040(E)). The code we read does not say whether the solar setback still applies there, so ask Planning.

Bathrooms and kitchens in a shop have their own rules (DCC 18.116.040(B), (C) and (D)):

  • A full bath is barred unless you sign and record a Deschutes County restrictive covenant that bars using the building as a dwelling.
  • The same bar applies to a sink outside a bath with a dishwasher or refrigerator, and to a sink outside a bath with laundry appliances.
  • With the covenant, you can install one of those three groups.
  • More than one group needs an approved land use permit with a finding that the use is allowed on your lot.
  • A kitchen needs that same finding.

If you want living space on the lot beyond the house, our rural ADU guide covers the county’s ADU rules.

The sections we read do not mention a half bath, so ask Planning. The county’s Onsite Authorization Application Guide lists “adding plumbing in a detached structure” as an example of when an Authorization Notice is required for an owner with an existing onsite septic system. It also says an Onsite Permit may be required, depending on the proposed changes. In the table above, one authorization line applies, not both, so ask the Onsite Wastewater Division which one fits a shop (fee schedule).

Two sources set the size where you need no building permit, and they differ. The 2023 edition of the Oregon Residential Specialty Code exempts a nonhabitable, one story, detached accessory structure up to 200 square feet and 15 feet high (ORSC section R105.2). Nonhabitable means not built to live in. On a parcel of 2 acres or more, the limit is 400 square feet if the structure sits at least 20 feet from all property lines and “regulated structures” (ORSC section R105.2). Ask Building Safety what counts as a regulated structure on your lot.

The county’s older accessory buildings brochure says a permit is needed over 200 square feet or over 10 feet high. It does not mention the 400 square foot allowance. So state code and the county’s older brochure differ. Confirm with Deschutes County Building Safety at (541) 388-6574 before you build without a permit. Electrical, mechanical and plumbing permits still apply where those systems are installed (state code interpretation 03-01).

The county considers an agricultural building exemption only in the Exclusive Farm Use (EFU), Forest Use (F-1 and F-2) or MUA-10 zones. It also needs land with a farmland or forestland tax deferral (county agricultural exemption guide). RR-10 is not on that list, so a personal shop on RR-10 land does not qualify.

R327 is the wildfire mitigation section of the Oregon Residential Specialty Code, which the county also calls fire hardening. The county says it is mandatory on all new dwellings and all new accessory structures beginning April 1, 2026, across unincorporated Deschutes County (county R327 page). The county’s handout says the required items must be clearly noted and detailed on the building permit drawings (county R327 handout).

Fire hardening is the use of building materials and practices that can reduce the risk of a home igniting due to embers, heat and flames from wildfires. It does not mean the home is fireproof (county R327 page). Many of these materials are already commonly used, such as double-pane windows, cementitious siding and Class B or better asphalt shingles (county R327 page).

The county’s FAQ names the three biggest changes. They are attic and crawlspace ventilation, protection for the underside of elevated decks, and protection for the exposed underside of eaves and enclosed soffits with any portion under 12 feet from grade (county R327 page). Products from the county’s accepted list must be specifically listed on the drawings and noted where they are to be installed (county R327 page). The page gives no cost figure, so have your builder or designer price it from the plans. Ask your builder to show where these items are on the plans.

A detached shop over 400 square feet is within R327 under all three published sources (county R327 page, text amendment page and state guidance). For a small nonhabitable structure of about 400 square feet, they state the exemption differently. The county page mentions a 15 foot roof height. The other two mention a 50 foot distance from buildings with living space. Confirm with Building Safety at (541) 388-6574.

Plan for a shop you don’t have yet. When our founder built his own home in Central Oregon, he sized the septic tank and drainfield with a future shop bathroom in mind. He also split a 400 amp electrical service, 200 amps to the house and 200 held for a future shop. That is his experience, not a rule. Ask the county before you size anything larger, because your site evaluation names the system the county requires.

The county's rules are one question. Your lot is another.

Our Due Diligence page explains SiteFacts Reports, which cover a lot's soils, utilities, zoning and permits. A real person responds within 24 business hours.

What permits do you need, and in what order?

The county lists what comes before the building permit (county building permit steps). That is land use requirements through Planning where they apply, an approved septic system or approval to install one where that applies, driveway access, and an Oregon ePermitting account. The county publishes no numbered order, so the list below follows its list and posted review times.

  1. Land use check with Planning, where it applies. Planning applications cannot be submitted through Oregon ePermitting (county Planning application page).
  2. Septic site evaluation, then the onsite permit, where septic applies. The county posts onsite permit review at 4 to 6 weeks after a 1 week intake (county processing times).
  3. Driveway access permit, which must be obtained before building permits issue where the driveway meets a public road under county jurisdiction (driveway information sheet). You may apply with the building application, and posted review is 3 weeks (building application guide).
  4. Oregon ePermitting account. The county’s instruction reads, “Homeowners, make sure to associate the Homeowners Licenses to your account” (county building permit steps). The county’s Oregon ePermitting FAQs page links a video titled “Homeowner Instructions for Oregon ePermitting.” In practice this account comes first, because the site evaluation application is also filed through it (Site Evaluation Application Guide). Our Oregon ePermitting guide walks through it.
  5. Building permit on Oregon ePermitting. The county withdraws incomplete applications (building application guide). Posted Planning review is 10 days when no additional Planning permits are needed, and building review is 8 to 9 weeks, run at the same time (county processing times).

These are queue times for a complete application, last updated July 15, 2026, and the county says they can vary (processing times page). Our Deschutes County permit guide has the detail.

How do you choose a builder for your land?

Start by checking the builder’s license on the CCB license search. CCB is the Oregon Construction Contractors Board. Oregon law says a contractor who undertakes or offers to do residential work must hold a current CCB license with a residential endorsement, unless an exemption applies (ORS 701.021).

A contractor may not do residential construction work for an owner without a written contract if the price exceeds $2,000 (ORS 701.305). When a written contract is required, the contractor must deliver three notices on or before the contract date. They are the Consumer Protection Notice, the Notice of Procedure and the Information Notice to Owner About Construction Liens (OAR 812-012-0130 and the CCB notices chart).

You can serve as the contractor on property you own, with conditions. State law exempts that work from CCB licensing, unless it is done in pursuit of an independent business with the intent of offering the structure for sale (ORS 701.010). When an owner applies for a residential building permit, the permit office supplies an Information Notice to Property Owners About Construction Responsibilities, and the owner signs a statement before the permit issues (ORS 701.325). The notice covers tax rules, workers’ compensation insurance on workers, and liability and property damage insurance. Confirm the current text with the CCB.

In our experience, the owner assumes the builder asked the hard questions, and the builder assumes the owner knows the property. Bring your zone and overlay zones, your site evaluation report, your permit history and your CC&Rs to the first meeting. Ask who files the permits, whether the plan was checked against your setbacks, and who pays if the county asks for changes. We do not recommend or rank builders.

What about power and water?

Power depends on which utility serves your lot. Central Electric Cooperative and Midstate Electric Cooperative each confirm on their own pages that they serve parts of Deschutes County (Central Electric service area and Midstate Electric service area). Other providers may serve parts of the county, so confirm the provider for your lot. To start new service, Central Electric has a new service application and lists Engineering Services at 541-312-7778. Midstate Electric has a New Construction page.

Deschutes County does not permit wells or water usage, and it points well questions to the Oregon Water Resources Department at 541-306-6885 (county Code Enforcement page). To see whether a well report is on file, search the state’s Well Report Query by well label, by township, range and section, or by county and tax lot. No report on file does not prove there is no well.

When does it make sense to get help?

It makes sense when you would rather not do the permit filing yourself. We file building permits in unincorporated Deschutes County. The city or county that issues the permit approves it.

Our permitting service offers building permit package submittals from $750. It includes a SiteFacts Report, which covers the lot’s soils, utilities, zoning and permits. The site plan is not included. Basic site plans for unincorporated lots: from $500. They are drawn from county records and your information, not a survey and not engineered.

We submit your application and respond to the county when it comes back with corrections. Every correction round is at no added fee.

We do not file land use applications, do septic site evaluations or design septic systems. We submit a septic permit when you give us a completed design. We are not your builder. The owner or your licensed builder makes and signs every construction decision.

We submit your building permit and answer the county's corrections.

Tell us about your project. A real person responds within 24 business hours.

Quick answers

Do you need a septic site evaluation before a building permit?

If your lot needs a septic system, the county says a site evaluation is required before it can issue onsite wastewater or building permits, unless a valid one is on file (county site evaluation page). Confirm with Deschutes County.

Can you build a shop before the house?

In a limited form, unless the house is established or applied for. The code lists three cases where a permit can issue with no primary use. Two are narrow: a ramada or carport, and permits to correct existing violations. The one that fits a shop covers a structure, or structures, of no more than 2,000 square feet combined. Each must have no windows, only one floor, an operable garage door, no plumbing or stack vents through the roof or walls, and no need for plumbing or mechanical permits. This applies if all other criteria for issuance are met (DCC 18.116.040(A)(1)(c)).

Can you put a bathroom in a shop?

A full bath needs a recorded covenant that bars using the building as a dwelling. So does a sink outside a bath with a dishwasher or refrigerator, or with laundry appliances, and the covenant covers one of those groups only. More than one group needs an approved land use permit with a finding that the use is allowed on your lot, and a kitchen needs the same finding (DCC 18.116.040(B), (C) and (D)). The county’s Onsite Authorization guide lists adding plumbing in a detached structure as an example of when an Authorization Notice is required for an existing septic system. An Onsite Permit may also be required (county authorization guide).

Will the county finish a site evaluation in 30 days?

The county attempts 30 days and says state rules set no required timeframe (county site evaluation page).

Does the county enforce HOA rules?

County Code Enforcement says it is not able to assist with enforcing HOA requirements or any civil requirements that are not County Code (Code Enforcement page).

// Next step

Talk to us about your lot.

A real person responds within 24 business hours.

// Below the Surface · free monthly email

Get one real lot case a month.

Below the Surface is the monthly email from SiteFacts, our land due diligence product: a lot story, a due diligence tip and the news worth knowing if you build, sell or invest in land. It comes out the second Wednesday of the month.

By submitting you agree to the SiteFacts Privacy Policy. We never sell your info.