Wildfire hardening applies to new dwellings
R327 (Oregon's wildfire-resistant building rules) is required on new dwellings and new accessory structures from April 1, 2026, in unincorporated Deschutes County and Sisters, not remodels or additions. Small accessory buildings may be exempt (county R327 page).
Septic decides the order
On an existing lot without sewer, a site evaluation precedes any building permit, and it can't be done on frozen or snow-covered ground (county checklist).
South county septic can need nitrogen reduction
For a new system or major repair in southern Deschutes County, the county says this typically means nitrogen-reducing technology (county page).
Confirm each item with Building Safety: (541) 388-6574.
In our experience, plan septic first, land use second, building third. The septic result can change the design, so get it before final plans.
In our experience, pull the permit, septic and land use history before you design. Old approvals, such as a prior Landscape Management decision or an old septic record, changed the path on at least five of our projects.
A La Pine mailing address doesn't put a lot inside the City of La Pine. In our experience, a recent south county project with one got its land use and building permits from the county. Check city limits first.
On a lot outside a city, a SiteFacts Report covers its soils, utilities, zoning and permits before you commit.
If you own vacant land here and plan a house and a shop, our land owner's guide covers septic, setbacks and the county's shop rules.